Fan Locked
Meaning: Inverter fan is locked or not functioning properly.
Check if fan is blocked by dust/debris. Restart inverter. If persists, fan replacement needed.
Lookup fault codes, meanings, and recommended action steps for Growatt, Deye, and Huawei solar inverters installed across Myanmar.
Meaning: Inverter fan is locked or not functioning properly.
Check if fan is blocked by dust/debris. Restart inverter. If persists, fan replacement needed.
Meaning: Internal inverter temperature exceeds safe limit.
Ensure adequate ventilation, clear heat sinks, reduce heavy continuous load during hot hours.
Meaning: Battery voltage exceeded maximum operating threshold.
Check BMS settings, verify charge controller configuration and battery bank voltage.
Meaning: Battery discharged below cut-off threshold.
Allow solar or grid recharge. If battery does not recover, inspect battery health/cells.
Meaning: Short circuit detected on AC output / load side.
Turn off AC breaker. Check wiring and disconnected loads one by one to isolate the faulty appliance.
Meaning: Output voltage above permissible inverter regulation range.
Disconnect load, restart inverter. If error returns without load, internal power stage failure.
Meaning: Inverter ran in overload state longer than allowed duration.
Reduce appliance load. Match continuous appliance wattage to inverter rating.
Meaning: DC Bus voltage exceeded safe operating limit.
Check PV array open-circuit voltage (Voc) under cold weather; verify it does not exceed max MPPT limit.
Meaning: Inverter failed to charge internal DC bus capacitors during startup.
Restart system. If fault persists, internal circuitry issue requiring repair.
Meaning: Inverter hardware overcurrent detected.
Check for motor/compressor surge spikes. Restart and test with lower surge loads.
Meaning: DC bus voltage dropped below operational limit during power delivery.
Check battery discharge rate and PV input stability during high load steps.
Meaning: AC output voltage dropped below threshold under load.
Reduce connected load. Inspect AC output terminal connections.
Meaning: DC bus failed pre-charging before grid connection.
Inspect DC wiring, battery connection, and restart inverter switch.
Meaning: Ground fault current or leakage current too high.
Check PV cable insulation, solar panel frames grounding, and moisture in junction boxes.
Meaning: Utility grid / generator frequency higher than standard parameter.
Check generator governor or grid parameter settings in inverter setup.
Meaning: Grid or generator frequency dropped below operating window.
Verify generator output frequency and stability under heavy load.
Meaning: Hardware AC overcurrent protection triggered.
Check for heavy motor starts or short circuits on backup AC output ports.
Meaning: Excessive DC current on PV or battery input.
Verify PV string configuration and battery charge/discharge current limits.
Meaning: PV array insulation resistance to ground is below threshold (ISO fault).
Inspect PV DC wiring for damaged jacket, conduit water ingress, or pinched solar wires.
Meaning: Internal DC bus voltage exceeded limit.
Verify PV string Voc under cold ambient temperatures does not exceed inverter maximum.
Meaning: Internal power module heatsink temperature too high.
Clean air filters and heatsink fins. Verify installation clearance requirements.
Meaning: Grid voltage is higher than acceptable range.
Measure grid voltage with multimeter; adjust local grid code overvoltage settings if permitted.
Meaning: Battery voltage too low for normal operation.
Recharge battery bank. Check battery breaker and cable connections.
Meaning: Communication between inverter and lithium battery BMS interrupted.
Check RS485 / CAN communication cable, baud rate, and lithium battery protocol settings.
Meaning: PV array open-circuit voltage is higher than the max inverter input voltage.
Immediately disconnect PV switch. Recalculate string length and remove excess panels per string.
Meaning: DC arc detected in PV string wiring.
Check PV connectors (MC4), crimps, and junction boxes along the string for loose contacts or damage.
Meaning: Grid voltage higher than safety limit or grid disconnected.
Check AC breaker. If grid is present, check AC voltage level and grid standard settings.
Meaning: Grid voltage lower than safety limit (outage or brownout).
Normal during power outages in Myanmar. Inverter switches to island/backup mode if configured.
Meaning: Short circuit between PV string and ground.
Inspect DC lines for ground leakage, degraded cable insulation, or water in rooftop conduits.
Meaning: Internal components exceeded operational temperature.
Ensure inverter is installed away from direct afternoon sunlight; clean cooling fins.
Meaning: Inverter self-test failed or internal hardware fault.
Power cycle both AC and DC isolators for 5 minutes. If persists, contact certified service support.